One of my clients recently had a case which I am explaining below and if you are stuck in such similar situation, here is what to do.
Note: Due to attorney-client privilege, I cannot disclose complete case details or identify the actual parties involved. However, I am sharing the essential facts and legal approach so that if you find yourself in a similar situation, you can understand the available solutions and legal remedies.
Rohan Gupta, a software professional from Pune, had booked a 2BHK flat with Lodha Developers in their township project in Wakad around early March 2022. The builder had promised possession by December 2023. But by February 2025, not only had possession not been handed over — the construction itself had stalled for months, with the builder offering vague reassurances and no written commitment.
Rohan had already approached a local civil lawyer who drafted a legal notice to the builder. The builder's team acknowledged it and then went completely silent. Nothing moved. Frustrated, Rohan reached out to Advocate Sudhir Rao after a colleague recommended him specifically for RERA matters.
The approach shifted significantly from that point. A formal complaint was filed before the Maharashtra Real Estate Regulatory Authority, citing specific violations under the Real Estate (Regulation and Development) Act, 2016. An application for interim relief was also filed, seeking a status quo order on the project. The RERA Authority issued notices to the builder, and within a few months, the builder was directed to either complete construction by a revised deadline or refund the full amount with interest at the prescribed rate. Rohan opted for the refund route. The order came through, and recovery proceedings were initiated. The earlier general legal notice approach had not moved the needle at all — but a focused RERA strategy, grounded in the specific provisions of the Act and the Authority's procedural expectations, produced a concrete, enforceable outcome.
Advice in Such Cases
Consult with Lawyer: The very basic and important step to start is talk to Lawyer / advocate. You should not hesitate in paying his consultation fee i.e. might be in range of Rs. 10,000 to 50,000 depends case to case. He is helping you in this situation to come out. He is expert in the domain and can help you explain the procedure which you might have never explored. A good lawyer can get the issues resolved much faster than you think.
Gather all documents first: Before you file anything, pull together every piece of paperwork — the Builder-Buyer Agreement, payment receipts, allotment letter, any emails or WhatsApp messages from the builder, and the RERA registration number of the project. Filing an incomplete complaint slows things down considerably. And here's the thing, buyers routinely underestimate how much a missing document can stall a complaint that should be straightforward.
Do not wait too long: RERA has a limitation period, and delay weakens your negotiating position as well. If possession is overdue, start the process. Don't wait for the builder to "come around."
Engage an advocate with domain-specific experience: RERA proceedings have their own procedural rhythm — evidence requirements, interim application strategy, and compliance enforcement are quite different from general civil litigation. Now, before you act, understand this clearly: a practitioner who regularly handles RERA matters will be far more effective in anticipating procedural hurdles and structuring the complaint correctly from day one. A general property lawyer isn't always the right fit here.
Applicable Sections of Law
- Section 18, Real Estate (Regulation and Development) Act, 2016: Entitles the allottee to a full refund with interest if the promoter fails to complete the project or hand over possession by the agreed date.
- Section 31, RERA, 2016: Governs the filing of complaints before the Real Estate Regulatory Authority by aggrieved allottees, associations, or resident welfare associations.
- Section 71 and 72, RERA, 2016: Provide for adjudication of compensation claims by the Adjudicating Officer and prescribe the factors for determining compensation.
- Section 36, Specific Relief Act, 1963: Allows for preventive relief by way of injunction — relevant where a buyer seeks to restrain the builder from alienating or mortgaging the disputed property during proceedings.
Jurisdiction — Where to File the Case
RERA complaints are filed before the Real Estate Regulatory Authority of the state where the project is registered. Each state has its own RERA — Maharashtra RERA (MahaRERA), Karnataka RERA, Haryana RERA, and so on. The territorial jurisdiction is determined by the location of the project, not where the buyer resides. For compensation claims, the Adjudicating Officer under Section 71 has jurisdiction. Appeals from RERA Authority orders go to the Real Estate Appellate Tribunal, and from there, to the concerned High Court. Frankly, getting jurisdiction right from the outset is critical — filing before the wrong forum wastes time and may affect your limitation.
Limitation Period
The RERA Act, 2016 does not prescribe a specific limitation period for filing complaints before the Authority. But the general principle under the Limitation Act, 1963 — and confirmed in practice by several RERA Authorities — is that undue delay can be held against a complainant. For compensation claims, acting promptly after the cause of action arises (typically the agreed possession date) is strongly advisable. Delay in approaching the forum has, in several matters, been used by builders to argue prejudice. If there's a delay, a condonation application with a proper explanation must accompany the complaint. Don't assume delay will be overlooked automatically.
Interim Reliefs Available
Under Section 37 of the RERA Act, 2016, the Authority has the power to issue such interim orders as it deems fit to protect the interests of allottees during the pendency of a complaint. This includes restraining the promoter from creating third-party interest in the unit, directing status quo on construction activity, and preventing diversion of funds collected from buyers. For compensation-linked matters before the Adjudicating Officer, Order 39 Rule 1 and Rule 2 of the Civil Procedure Code, 1908 principles are applied by analogy. Make no mistake, securing interim relief early in the proceedings is tactically important — it prevents the builder from muddying the waters while the case is pending.
If You Are the Victim
- Verify that the builder's project is registered under RERA and note the registration number — this is the foundation of your complaint.
- Document every communication with the builder: save emails, WhatsApp messages, letters, and any oral commitment that was later reduced to writing.
- File the complaint before the concerned State RERA Authority — do not rely solely on a legal notice to the builder, as notices without formal proceedings rarely produce compliance.
- If the builder has collected money without RERA registration or in violation of the Act, this can constitute an additional ground for complaint and enhanced relief.
- If the RERA order is passed and the builder does not comply, apply promptly for recovery proceedings — RERA orders are recoverable as arrears of land revenue in most states, which is a significant enforcement lever.
Documents You Must Keep Ready
- Aadhaar Card and PAN Card of the complainant
- Builder-Buyer Agreement / Allotment Letter
- All payment receipts, bank statements showing payments made to the builder
- Brochures, advertisement materials, and any possession date commitments in writing
- Correspondence with the builder (emails, letters, WhatsApp screenshots)
- RERA registration certificate of the project (downloadable from the state RERA portal)
- Demand letters issued by the builder and any replies given
- Floor plan and unit details as per the agreement
What Evidence Is Required?
- Primary evidence: The original Builder-Buyer Agreement — this is the single most important document, as it establishes the agreed possession date and payment schedule.
- Proof of payments made (bank statements, NEFT/RTGS confirmations, cheque copies)
- RERA project registration documents showing the committed timeline
- Site photographs or video evidence showing the actual stage of construction
- Written communications where the builder acknowledged delay or gave revised timelines
- Any correspondence where refund was sought but denied
- Secondary evidence: Witness statements from co-allottees facing the same delay — RERA Authorities often consider collective evidence of delay across multiple units when assessing the builder's default pattern.
How Courts Typically Approach Such Cases
RERA Authorities across states have generally taken a consumer-protective stance. Where possession dates are clearly missed and the builder can't demonstrate force majeure or an approved extension, orders for refund with interest — typically at the State Bank of India's Marginal Cost of Funds Based Lending Rate plus two percent — have been passed consistently. As held in Newtech Promoters and Developers Pvt. Ltd. v. State of UP, 2021 (Supreme Court), RERA is a beneficial legislation and its provisions must be construed in favour of allottees. And here's why that matters: Adjudicating Officers assess compensation on a case-by-case basis, weighing the extent of delay, financial loss to the buyer, and the builder's conduct during proceedings. The builder's attitude in the hearing room often speaks as loudly as the documents.
Timeline of Legal Process
- Week 1-2: Compile documents, verify RERA registration, send a final demand notice to the builder (optional but recommended before filing)
- Week 3-4: File complaint before the State RERA Authority online or in person; pay filing fees
- Month 1-2: Authority issues notice to the builder/promoter; builder files reply
- Month 2-4: Hearings before the RERA Authority; evidence and arguments placed on record
- Month 4-6: Order passed by the RERA Authority (the Act mandates disposal within 60 days, though in practice timelines vary by state)
- If builder does not comply: File recovery application; recovery officer proceeds as per the state's land revenue mechanism
- Appeal: Either party may appeal to the Real Estate Appellate Tribunal within 60 days of the order; further appeal lies before the High Court
- Total realistic timeline: 6 to 18 months from filing to recovery, depending on the state and the builder's conduct
Understanding the Costs
The total cost of a matter like this varies significantly from one case to the next — it depends on the complexity of the dispute, the forum involved, the number of hearings, and the specific facts of your situation. There is no single fixed figure that applies to everyone.
A professional advocate can give you an accurate estimate only after reviewing all your facts and documents in a consultation.
Can the Matter Be Settled Out of Court?
Yes. Many RERA matters are resolved through negotiated settlements, particularly after the complaint is filed and the builder realises the Authority is taking cognizance. Section 89 of the Code of Civil Procedure, 1908 principles of compromise apply to the extent they are consistent with RERA proceedings. Settlement through mediation is possible, and some state RERA Authorities have conciliation cells. A Lok Adalat under the Legal Services Authorities Act can also take up pre-litigation or pending RERA matters and pass awards that are final and non-appealable. Settlement is advisable when the builder offers a fair refund with reasonable interest, or when possession with compensation is genuinely on the table — but only after your advocate reviews the proposed terms carefully. Never sign a settlement deed without counsel.
Common Mistakes People Make
- Waiting too long to act: Many buyers wait years hoping the builder will deliver. By then, the project may be in insolvency proceedings or the builder's assets may be dissipated.
- Relying only on legal notices: A legal notice to the builder, without a formal RERA complaint, is rarely sufficient. Builders routinely ignore or give non-committal replies to notices.
- Not verifying RERA registration: Some buyers file complaints only to discover the project was not registered under RERA — significantly limiting available remedies. Always verify on the state RERA portal before booking.
- Signing revised agreements or acceptance letters: Builders sometimes ask buyers to sign revised timelines or "goodwill" letters that can waive your right to claim delay compensation. Never sign anything without your advocate reviewing it.
- Engaging an advocate without RERA-specific experience: RERA proceedings are distinct from ordinary civil suits. The evidence format, interim relief strategy, the way defaults are framed, and the enforcement mechanism post-order all require familiarity with RERA practice specifically. A general property lawyer may handle the basics, but the procedural and strategic nuances that determine outcomes in RERA matters are built through regular practice in this domain — and gaps in that experience can affect how effectively your case is pursued.
- Posting grievances on social media before proceedings: This can complicate matters, attract defamation responses from builders, and sometimes prejudice settlement discussions.